Jefferies forecasts 12.9 GW of new North American datacenter capacity in 2026

1 article1 sourcesince Oct 16Last article 3h ago ·

Overview

AISummary of 1 article

Jefferies analyst Jonathan Petersen forecasts 12.9 GW of new North American datacenter IT capacity in 2026 and 18 GW in 2027, according to a report covered by The Next Platform.

The forecast is based on about 65 GW under construction and 361 GW of announced projects.

Petersen says labor shortages, equipment manufacturing, power interconnects and local politics will delay or cancel many of those projects, which is why the expected build-out is far below the announced total.

Written by AI from the articles below · updated Oct 16, 12:32 PM ET

Check the sources:

Article timeline

The articles in this story. Times are ET.

Oct 16
  1. The Next PlatformNews
    Jefferies forecasts 12.9 GW of new US datacenter capacity in 2026

    AIJefferies analyst Jonathan Petersen forecasts 12.9 GW of new North American datacenter IT capacity in 2026 and 18 GW in 2027, citing about 65 GW under construction and 361 GW of announced projects. He says labor shortages, equipment manufacturing, power interconnects and local politics will delay or cancel many projects.

Heat trend

Current comparable heat
9
Peak comparable heat
10Oct 16, 1:00 PM ET
Change in past 24 hours
–

The trend compares only continuously observed participants, so its scope may be smaller than the current heat total. Hover or tap for hourly heat; use arrow keys with a keyboard.