The biggest risk to the US data center buildout is already in effect in one state.
“The single biggest risk isn’t a single candidate, because in many cases both parties and candidates want developers to accept stricter terms.”
“In the case of Texas, it’s a freeze that already exists. Texas stopped issuing TCEQ permits to data center projects at the end of September, on top of an ERCOT interconnection audit that started in August.”
“Texas alone is close to 30% of US additions in 2028. So a few months of lost time in that one state, that one market, could move the national number.”