Oracle's 1GW AI infrastructure deal: ~$80B contract value, ~28% ROI

AIOracle's investor day slides put the economics of 1GW of AI infrastructure at about $80B in contract value, ~$37B capex, and ~$16B annual revenue. The deal shows a 5-year average contract, ~35% gross margin, ~34% operating margin, and ~28% ROI. Rohan Paul calculates that the ROI implies roughly a 3.6-year cash payback, and notes the footnote says the contracts are cost-plus.
Rohan PaulVerified on X
@rohanpaul_ai
View on X

For Oracle, what 1GW of AI infrastructure earns. ~$80B contract value, ~$37B capex, ~$16B annual revenue, 5-year average contract, ~35% gross margin, ~34% operating margin, ~28% ROI.

A 28% ROI implies about a 3.6-year cash payback on a 5-year contract, and the footnote says these contracts are cost-plus.

- From Oracle Investor day slide deck held yesterday, Oct 28, 2026, in Las Vegas.