Why Texas Is Pausing Data Center Grid Approvals and What Comes Next

AITexas grid operator ERCOT saw its large-load interconnection queue grow from 63 GW at the end of 2024 to 474 GW by June, about 90% from data centers, and then the state paused new approvals. The author argues the pause reflects low-quality speculative requests, cost-allocation disputes, and reliability limits on a grid that is largely isolated.
Read the original a16z.news
Source details

a16z News · Ryan McEntush · a16z.newsPublished · added here

Original title: Why Texas Is Making Data Centers Wait