View original post on X: Rohan PaulX· Pick63/100AI score63/100

Anthropic negotiates a second $45B compute deal with Nscale

AISummary

Anthropic is negotiating a second $45B compute deal with Nscale that would double its West Virginia reservation to 920 MW. The new contract covers another 460 MW building at Nscale's Monarch Compute Campus running Nvidia's Vera Rubin chips. The first contract, signed in August, is a 6-year, 460 MW lease with delivery starting in late 2027.

AIWhy it matters

The post links a possible second deal to Nscale's IPO filing and the schedule of its first building, showing how the value depends on delivery timing.

Post on XView on X
Rohan PaulVerified on X
@rohanpaul_ai

Anthropic is negotiating a 2nd $45B compute deal with Nscale that would double its West Virginia reservation to 920 MW.

This is for another 460 MW building at Nscale’s Monarch Compute Campus running Nvidia’s Vera Rubin chips, and Anthropic also holds a right of first refusal on the campus’s expected third building.

The first contract, signed in August, is a 6-year, 460 MW lease with delivery starting in late 2027, which averages $7.5B a year, or about $16.3M per MW.

Because Monarch’s first phase is designed for 1.35 GW across 3 buildings, Anthropic could end up holding the entire initial development.

Nscale’s IPO filing lists Anthropic agreements worth up to about $44.6B.

A second Anthropic deal would strengthen Nscale’s listing pitch, yet its value depends on Monarch energizing its first building and Vera Rubin racks on schedule in late 2027.

Source: Rohan Paul · x.comPublished · added here