We looked at each Texas site planning on-site power that falls under Governor Abbott’s Sept 21 directive, which tells TCEQ to stop issuing any permit tied to a datacenter until ERCOT finishes its review, and found six campuses, 8.7GW in all, needing air permits during the pause. (1/5)🧵
Six Texas datacenter campuses needing 8.7GW of air permits face pause
AISemiAnalysis identified six Texas datacenter campuses with on-site power that need air permits during Governor Abbott's September 21 directive. The directive tells TCEQ to stop issuing datacenter-linked permits until ERCOT completes its review.