# Epoch AI estimates Huawei's Horinger data center at 81,000 H100-equivalents

> Original title: What Huawei’s Horinger data center reveals about China’s compute gap

- Source: Epoch AI · The Epoch Brief
- Published: 2026-11-12T16:03:15.000Z
- Bad Influence: https://badinfluence.news/items/nql1ceeuhadlobbq7mp72pxaz
- Original: https://epochai.substack.com/p/what-huaweis-horinger-data-center

## Summary

Epoch AI estimates Huawei's Horinger AI data center in Inner Mongolia has about 81,000 H100-equivalents of compute, with a 90% range of 36,000 to 141,000. The estimate is based on satellite imagery and cooling equipment, which points to 286 MW of IT power capacity across four buildings. Colossus 2 in Tennessee has about 14 times as much compute.