# Why Texas Is Pausing Data Center Grid Approvals and What Comes Next

> Original title: Why Texas Is Making Data Centers Wait

- Source: a16z News
- Published: 2026-10-07T14:01:44.000Z
- Bad Influence: https://badinfluence.news/items/cn17ynym8z34a5wqsjofqfceq
- Original: https://www.a16z.news/p/why-texas-is-making-data-centers

## Summary

Texas grid operator ERCOT saw its large-load interconnection queue grow from 63 GW at the end of 2024 to 474 GW by June, about 90% from data centers, and then the state paused new approvals. The author argues the pause reflects low-quality speculative requests, cost-allocation disputes, and reliability limits on a grid that is largely isolated. He suggests flexibility, on-site power bridging to the grid, and better cost rules could help data centers connect.